Wet Plant Upgrade – Kermit, TX

Project Value: $10MM
Activities / Roles: General Contractor for turn-key installation.
Project Type: Brownfield

Project Description:
At NuBlu Energy, we’re committed to meeting the growing demands of our customers. Through our project, we successfully upgraded our wet plant process to handle 25% more feed. This expansion ensures that we can provide you with even more of the high-quality products and services you rely on.

Structural Integrity: Our commitment to quality extends to every aspect of our operations. As part of this project, we meticulously installed and modified steel structures to enhance the reliability and safety of our facilities.

Rock-Solid Foundation: The foundation of any great project is the concrete upon which it stands. We poured over 1500 cubic yards of concrete with precision and expertise, ensuring that our facilities are built to last.

Cutting-Edge Equipment: To complement our upgraded wet plant process, we installed over 2000HP of frac sand washing equipment. This advanced equipment ensures that our products meet the highest industry standards while enhancing our overall efficiency.

At NuBlu Energy, our commitment to innovation and quality shines through in every project we undertake. We are dedicated to exceeding your expectations and delivering top-notch products and services. Join us on our journey to set new standards in the industry and experience excellence with NuBlu Energy.

Project Highlights:
  • Upgraded wet plant process to accommodate 25% more feed.
  • Steel structure installation and modification.
  • Poured over 1500 cu. yd. of concrete.
  • Installation of 2000+HP of frac sand washing equipment